We have executed a wide range of design assignments in green energy and grid for clients in India and the Middle East.
2 GW, Al Dhafra, United Arab Emirates
300 MW + 600 MWh (BESS), Bikaner, Rajasthan
300 MW (BESS) + 220 kV SS, Bikaner, Rajasthan
260 MW, Bidar, Karnataka
250 MW, Tuticorin, Tamil Nadu
198 MW, Bidar, Karnataka
153 MW, Karur, Tamil Nadu
122 MW, Bidar, Karnataka
70 MW + 110 kV Substation, Ramanathapuram, Tamil Nadu
70 MW, Sibsagar, Assam
69 MW, Ausa
50 MW + 66 kV Substation, Serenje, Zambia
50 MW + 66 kV Substation, Morbi, Gujarat
50 MW, Bikaner, Rajasthan
50 MW, Lalitpur, Uttar Pradesh
45 MW + 66 kV Substation, Banaskantha, Gujarat
35 MW + 66 kV Substation, Patan, Gujarat
30 MW, Srikakulam, Andhra Pradesh
20 MW, Patan, Gujarat
20 MW, Anantapur, Andhra Pradesh
10 MW, Bhiwani, Haryana
10 MW, Virudhunagar, Tamil Nadu
10 MW, Patan, Gujarat
10 MW, Bap, Rajasthan
10 MW, Bap, Rajasthan
10 MW, Anantapur, Andhra Pradesh
10 MW, Anantapur, Andhra Pradesh
10 MW, Patran, Punjab
10 MW, Kurnool, Andhra Pradesh
5 MW, Chennai, Tamil Nadu
5 MW, Tuticorin, Tamil Nadu
5 MW, Gulbarga, Karnataka
1 MW, Sambhal, Uttar Pradesh
For our 70MWp solar power project in Zambia, Verdatriz played a crucial role in power plant design, power system studies and switchyard design. Their support throughout the design process and vendor evaluation was invaluable.
Ravi Palaniappan CEO, UltraGreen Corporation
Verdatriz acted as the EPC for our 6.3MWp solar power plant in Tamil Nadu. Their dedication and expertise were key to the successful commissioning of the project.
Jayabharathi Balamurugan Director, Daily Fresh Fruits India
Verdatriz served as our extended design arm for Virescent and supported us with high-quality, low-cost design. They performed owner's engineering review, due diligence, project monitoring and rectification design among other design activities over 2 years.
Atul Raizaada COO, Virescent InfrastructureWe engaged Verdatriz to perform a feasibility study for our proposed rooftop solar power plant. Their expertise and attention to detail gave us the confidence to proceed with the project.
Charu Koharwal AGM, Dhampur Sugar
We are grateful to Verdatriz for their pre-bid engineering support for the 2GW Al Dhafra solar power plant in the UAE. Their contribution was instrumental in helping us achieve the bid milestones and secure technical qualification.
Prewyn Kumar AGM, alfanar